How Multiskilled Crews Can Transform Construction Productivity in the Carolinas

How Multiskilled Crews Can Transform Construction Productivity in the Carolinas

For commercial contractors across North and South Carolina, the pressure to deliver more work with fewer available workers is not easing. Multiskilled construction crews offer one of the most practical, field-tested strategies to close that gap. Here is what the latest national research says, why it matters for Carolinas contractors right now, and how to get started.

Table of Contents

For commercial contractors across North and South Carolina, the pressure to deliver more work with fewer available workers is not easing. Multiskilled construction crews offer one of the most practical, field-tested strategies to close that gap. Here is what the latest national research says, why it matters for Carolinas contractors right now, and how to get started.

Key Takeaways

Multiskilled construction crews represent one of the fastest, most practical levers to improve construction productivity for commercial contractors operating across North and South Carolina. Rather than relying on hiring alone or burning out existing teams with overtime, multiskilling gives firms a disciplined way to get more direct work from every crew, every shift.

  • ABC National’s field research found that multiskilled workers increase time spent on direct construction work by nearly 40%, cutting idle time dramatically without sacrificing safety or quality. Labor shortages and material delays affect construction productivity, making this kind of efficiency gain critical.
  • For Carolinas contractors facing persistent craft shortages, especially along the I-85 and I-77 corridors, multiskilling paired with apprenticeship, safety training, and strong supervision is a workforce strategy, not a shortcut. Skilled and experienced workers boost construction productivity and reduce mistakes, and multiskilling builds on that foundation.
  • Multiskilled crews are especially valuable on industrial, healthcare, infrastructure, and fast-track commercial construction projects in Charlotte, the Triangle, and the Upstate.
  • This article gives executives a practical playbook: when multiskilling works, how it affects construction workers and construction firms, the safety guardrails required, and concrete first steps with ABC Carolinas.

Construction Productivity Pressures Facing Carolinas Contractors

The construction industry in the United States has struggled with productivity growth for many decades. A Richmond Federal Reserve brief noted that US construction productivity in 2023 was essentially the same as in 1948, a stagnation across the entire construction industry that stands in stark contrast to manufacturing and other sectors of the economy. While some subsectors have improved in recent years, overall construction productivity has not kept pace with capital inputs, technology investment, or demand.

In North and South Carolina, these national pressures are compounded by rapid regional growth. Charlotte, Raleigh, Durham, Charleston, and the Upstate are all absorbing population growth, industrial investment, and infrastructure demand at scale. Data center construction along the North Carolina corridor, EV and battery manufacturing facilities in South Carolina, and healthcare campuses across both states are driving enormous project pipelines.

Inadequate planning increases wait times and reduces productivity on job sites, and weather can halt outdoor work and disrupt schedules in the Carolinas’ humid climate. Project management and preconstruction planning are critical for minimizing delays, yet traditional approaches to boosting output are running into hard limits:

  • Labor scarcity: ABC estimates the national construction workforce shortage at 349,000 workers in 2026. In North Carolina, 59% of contractors report that labor shortages are delaying projects.
  • Aging workforce: Charlotte alone will need to fill an estimated 5,000 construction jobs over the next 30 years just for transportation and infrastructure work.
  • Compressed schedules: Industrial plants, healthcare facilities, and fast-track commercial buildings demand predictable delivery, and every idle hour compounds cost.
  • Margin pressure: Overtime, heavy subcontracting, and last-minute mobilizations erode already thin margins for smaller firms and large contractors alike.

These challenges are pushing owners and contractors to look beyond headcount and toward crew utilization, task sequencing, and multiskilled construction crews.

A group of construction workers collaborates on a large commercial building site, surrounded by steel framing and heavy equipment, showcasing the teamwork and skilled trades essential to the construction industry. The scene highlights the ongoing construction activities that contribute to productivity growth and infrastructure development.

What Multiskilled Construction Actually Means

Multiskilled construction means a worker retains full competency in a primary craft while also gaining verified, credentialed capability to perform specific adjacent tasks from related construction trades. Standardizing processes improves efficiency and reduces training time for construction crews, and multiskilling applies that principle at the individual worker level.

This is not about asking a carpenter to suddenly perform licensed electrical work. It is about planned, supervised skill expansion within safety and licensing boundaries:

  • A trained carpenter can set embedded anchors, install blocking, perform basic layout, or assist with nonenergized, low-risk tasks that support another trade.
  • A mechanical helper on a Greensboro medical office project who is also trained to handle basic rigging, material staging, or layout for concrete embed supports when the primary trade workfront is blocked.
  • An electrical helper trained to install conduit positioning, assist with cable tray support functions, or pull wire in nonenergized environments (within licensing limits).

Multiskilled workers typically use two to three different skill classifications in a single day, sometimes as many as six. Collaboration and communication among teams reduce errors and improve project outcomes, and multiskilling formalizes that collaboration at the task level. Continuous workforce training enhances safety and reduces downtime on construction sites, which is why this model insists on documented competency rather than improvised “odd jobbing” on a busy site.

The distinction matters: in a disciplined model, responsibilities are planned, documented, and supported by training. In an informal model, they are improvised, creating quality drift and safety risk.

What ABC National’s Field Research Shows About Multiskilled Crews

ABC National released a landmark field study on multiskilled construction, with results reported by Construction Executive. The study represents the largest dataset to date documenting how multiskilling relates to construction productivity, schedule performance, staffing needs, and safety across real job sites.

The headline findings are significant:

  • Multiskilled workers spent roughly 39% more time on direct construction work (installation, layout, material handling) than traditionally organized one-trade crews.
  • Active-work idle or waiting time dropped by approximately 68% for multiskilled crews.
  • To accomplish the same sequence of tasks with single-trade crews, firms would have needed 45 to 72% more workers, a staggering inefficiency in a market where every worker counts.
  • Workers spent about 36% of observed crew time on construction activities outside their primary trade, showing how much productive capacity cross-training unlocks.

Safety programs help maintain productivity by preventing disruptions, and the study confirmed this: over roughly 33.2 million work hours, multiskilled participants posted a Total Recordable Incident Rate of 0.74, 57% below the industry benchmark. The observed cohort had no fatalities.

Effective site supervision directly influences construction productivity by improving coordination, and the study reinforced that multiskilling works best under strong field leadership. Implementing a culture of continuous improvement can elevate overall project performance, and multiskilled crews embody that principle by continuously expanding what each worker can safely contribute.

The research also found benefits for individual construction workers: higher earnings potential, broader career paths, more consistent hours, and more chances to lead small teams, a powerful combination for recruitment and retention.

Why Multiskilled Crews Matter Now in the Carolinas Construction Industry

The national data is compelling. But what makes multiskilled construction especially relevant for the Carolinas right now is the intersection of growth, complexity, and workforce pressure that defines the region’s commercial construction sector.

Charlotte is absorbing massive commercial, industrial, and infrastructure investment. The Research Triangle continues to see healthcare, life sciences, and technology development at scale. Upstate South Carolina is a hub for advanced manufacturing. Along I-85, I-77, and I-95, contractors compete for the same shrinking pool of craft labor to staff projects ranging from distribution centers to hospital expansions.

Merit shop philosophy emphasizes competition based on merit, and multiskilling aligns directly with that principle: it rewards workers who invest in their own development and gives firms the flexibility to assign the best available person to the task at hand. The philosophy supports open shop labor agreements, which allow contractors to design their own training programs and crew structures without restrictive work rules. Merit shop advocates for skilled labor training and development, and multiskilling is one of the most effective ways to act on that commitment.

It promotes fair bidding practices in construction projects because firms with multiskilled crews can bid more accurately, knowing their labor utilization will be higher and their exposure to idle time will be lower. Merit shop principles help reduce project costs and improve quality by eliminating the overhead and delays that come from rigid single-trade staffing.

Technology like digital tracking and field reporting can optimize workflows on construction sites, and when paired with multiskilled crews, these tools make it easier to plan task assignments, monitor crew utilization, and track productivity gains in real time.

Consider two Carolinas scenarios:

  • A design-build healthcare campus near Raleigh where mechanical and structural trades frequently intersect, and shutdown windows are strict. Multiskilled helpers could perform layout, embed work, and blocking without waiting on mechanical journeymen held up by structural delays.
  • A battery manufacturing facility in Spartanburg County with overlapping electrical, mechanical, and structural installation phases. Multiskilled crews can accelerate secondary tasks, reduce schedule float, and keep production on track.

Where Multiskilled Construction Boosts Productivity the Most

Not every project or phase benefits equally from multiskilling. The greatest construction productivity gains come on projects where trades overlap frequently, schedules are tight, and small critical-path tasks often create bottlenecks.

  • Industrial and manufacturing projects along the I-85 corridor in both states: mechanical, electrical, and structural tasks overlap constantly. Building Information Modeling (BIM) helps detect clashes before construction begins, and multiskilled crews can resolve minor field conflicts without waiting for a different trade to mobilize. Adopting lean construction principles eliminates waste across materials, labor, and time on these large, complex builds.
  • Healthcare and life sciences facilities in Charlotte, Winston-Salem, and the Triangle: complex phasing and strict downtime windows mean multiskilled crews ready to perform several tasks during limited access periods keep the schedule on track. Just-in-Time (JIT) delivery minimizes waste and improves site organization, and multiskilled workers can receive and stage materials across trade lines.
  • Infrastructure and public works, including highway, bridge, and utility upgrades across the Carolinas: multiskilled field crews can shift between forming, reinforcement placement, finishing, and minor equipment tasks without waiting on multiple subcontractors. Efficient material handling and logistics are crucial to maintaining workflow on job sites like this.
  • Fast-track commercial and data center projects where delays carry high cost: multiskilled crews reduce friction in small but critical tasks (layout, sleeves, embed placement) that often hold up progress for days if a single-trade specialist is unavailable. The same bottleneck logic can also apply to residential work when specialized labor is not available.

An aerial view captures a bustling industrial construction project, showcasing multiple cranes and various active work areas where construction workers are engaged in different tasks. This dynamic scene reflects the overall productivity of the construction sector, highlighting the collaboration of skilled trades and construction firms in developing vital infrastructure.

How Multiskilled Crews Improve Day-to-Day Construction Productivity

In practice, multiskilled construction changes the daily rhythm of the jobsite. Fewer stoppages, faster responses to minor issues, and fewer small delays that compound into lost days, while a safer, better-planned site helps workers maintain focus on assigned tasks.

Daily meetings increase communication and help avoid delays in construction projects, and when combined with multiskilled crew planning, they become even more effective. Teamwork and communication are essential for ethical construction practices, and the multiskilled model puts those values into action every shift. Research shows that 43% of employees value a strong work ethic for success, and multiskilled workers tend to embody that ethic because they take pride in broader capability.

Here is what contractors can expect from a well-implemented multiskilled strategy:

  • Idle time reduction: The ABC study documented a 68% drop in active-work waiting time. Workers pivot to preplanned secondary tasks when their primary workfront is blocked.
  • Higher crew utilization: Firms keep a core crew productive even when a particular trade’s scope is temporarily paused, because those workers can contribute to adjacent construction work.
  • More predictable labor costs: Fewer emergency call-ins, less overtime, reduced re-mobilization expenses for smaller projects and large ones alike.
  • Better schedule performance: Fewer RFIs tied to missing small tasks, less trade stacking, and more resilient project timelines.
  • Worker satisfaction: Broader variety of work, more skill development, and more leadership opportunities improve retention and reduce recruiting costs.

Ethical practices improve project delivery in construction, and construction ethics promote safety and quality. When workers understand their roles, boundaries, and growth paths, the entire team performs at a higher level. The productivity gains come from good planning, realistic scope definitions, and intentional task assignment, not from asking people to do “whatever is needed.”

Safety, Quality, and Risk Guardrails for Multiskilled Construction

Safety and quality are nonnegotiable in construction. Multiskilled strategies must align with OSHA regulations, state licensing rules in North Carolina and South Carolina, and company safety programs.

Safety training reduces workplace accidents by 30%, and that investment matters even more when workers expand their task range. Proper safety training can prevent falls, trips, and slips, which remain among the leading causes of injury on commercial job sites. Following safety protocols creates a healthier work environment, and completing workforce safety training before any new task assignment can reduce accidents.

Key guardrails include:

  • Licensing compliance: Workers only perform tasks they are trained and authorized to do. Fully qualified personnel handle high-hazard work (energized electrical tasks, crane operation). Ethical standards help prevent construction fraud and corruption, and respecting licensing boundaries is central to that commitment.
  • Written scopes: Each multiskilled worker’s authorized tasks are documented, reviewed with supervisors, and updated as training advances.
  • Inspection checkpoints: A skilled specialist must inspect certain tasks. Passing off work without verification creates unacceptable quality risk.
  • Daily huddles and toolbox talks: Field leadership clarifies roles for the day, reviews any changes, and reinforces safety expectations.
  • Fatigue and role confusion management: Strong foremen and superintendents monitor workload, prevent scope creep, and intervene when a task should stay with a specialist.

For example, a multiskilled worker in Columbia might be trained to assist with pretask planning, basic rigging, and rough-in support work, but never to modify engineered systems or perform any task that requires a specific state license.

Building Multiskilled Construction Workers’ Capability Through Apprenticeship and Workforce Development

Sustainable multiskilled construction depends on long-term workforce development, not quick, informal cross-training. This is where ABC Carolinas’ apprenticeship and craft training programs are central.

ABC Carolinas offers nationally recognized apprenticeship programs that form the foundation of a multiskilled workforce. Apprenticeship programs can last up to four years, and in four years, apprentices can become highly skilled professionals ready to contribute across multiple phases of construction work. Apprentices earn a paycheck from day one, and construction workers can earn a paycheck from day one of training, which removes a major barrier to entry. Apprenticeships don’t add student debt, and construction education programs reduce it for trainees, making the skilled trades an accessible career path.

Apprenticeships provide hands-on skills employers need, and apprentices can become skilled professionals in high-demand fields across the construction sector. Education programs help connect trainees with hiring contractors, creating direct pipelines from training into productive employment. Workforce development creates pathways for construction industry growth and strengthens businesses and communities across both Carolinas.

A group of apprentices, wearing safety gear, are actively engaged in hands-on construction skills training within a workshop filled with various tools and building materials. This scene highlights the importance of education and practical experience in the construction industry, essential for developing skilled trades and ensuring productivity growth in construction projects.

How contractors can build this capability:

  • Start with a traditional merit shop apprenticeship in a skilled trade (electrical, HVAC, carpentry) as the core craft identity.
  • Add modules, short courses, and on-the-job training to expand capabilities into related tasks, always within safety and licensing boundaries.
  • Partner with ABC Carolinas to map common tasks, identify where multiskilling makes business sense, and design training plans from entry-level onboarding to advanced leadership development.
  • Track apprenticeship productivity improvements as learners gain the ability to support several phases of work on one site.

The region projects 15,000 to 20,000 annual openings for craft professionals through 2032. Building a multiskilled pipeline is not optional; it is a competitive necessity.

Implementing a Multiskilled Workforce Strategy in Your Construction Firm

Here is a step-by-step approach for Carolinas construction firms ready to pilot multiskilled crews:

  1. Select a pilot project: Choose one commercial or industrial job with frequent trade overlaps. Pick a superintendent and foreman who are open to planning, documentation, and coaching.
  2. Catalog core tasks by trade: Identify safe adjacent tasks that could be performed by multiskilled workers, then work with safety professionals and project managers to create clear boundaries and training needs.
  3. Align with training resources: Coordinate with ABC Carolinas to connect multiskilled roles with available apprenticeship tracks, NCCER-based training, and safety courses. Construction advocacy supports regulatory changes that improve the industry, and advocacy efforts aim to strengthen construction productivity standards at both the state and national level. Construction advocacy promotes ethical practices among industry professionals, ensuring that multiskilling is implemented responsibly.
  4. Set metrics: Track crew utilization percentages, hours spent waiting on other trades, rework rates, safety data, and worker feedback. Use those results to refine the model before broader rollout.
  5. Scale deliberately: Expand to additional crews and projects only after the pilot demonstrates measurable improvement in construction productivity, safety, and worker satisfaction.

Business Benefits Beyond Construction Productivity Growth

While improving construction productivity is the primary driver, multiskilled construction delivers additional value for firms operating in North and South Carolina.

Worker retention is a major advantage. Multiskilled workers often report higher job satisfaction, broader career paths, and more leadership opportunities. In a tight labor market, this translates directly to lower turnover and reduced recruiting costs. A successful career in the construction trades increasingly depends on versatility and the ability to grow, and multiskilling supports both.

Resilience matters, too. Firms with multiskilled crews are better prepared for supply chain delays, design changes, or inspector-driven rework because their crews can adapt without bringing in multiple additional subcontractors. Smaller firms especially benefit from this flexibility, since they often lack the bench depth to absorb unexpected schedule disruptions.

Member services include access to training programs that directly support multiskilled development. Members can participate in regulatory advocacy initiatives that shape the policies affecting the construction sector. Members can also connect through networking events that bring construction professionals in the Carolinas together. ABC Carolinas offers members networking opportunities, and networking events can support business growth in the construction industry. Members receive support to grow their businesses, and member services help deliver projects ethically and profitably.

Multiskilled strategies can also support diversity and inclusion goals in the construction industry by providing more entry points into the skilled trades and clearer progression from helper roles into fully qualified craft and leadership positions, building a stronger, more representative occupation pipeline.

How ABC Carolinas Can Support Your Multiskilled Construction Strategy

ABC Carolinas is the regional partner for construction firms that want to translate multiskilled research into practice. The association’s mission is to support merit shop contractors across North and South Carolina through safety training, apprenticeship and craft education, leadership development, and peer networking.

ABC Carolinas can convene member roundtables in Charlotte, the Triangle, and the Upstate to share lessons learned, field-tested practices, and policy updates that affect multiskilled construction workers and construction companies.

Your next step: Contact the ABC Carolinas workforce development team to explore apprenticeship options, enroll field leaders in supervision or safety courses, or join a peer group focused on field productivity and crew utilization. Multiskilled construction is built on the same values ABC Carolinas champions every day: free enterprise, safety, ethics, and helping members win work and deliver it profitably.

Frequently Asked Questions About Multiskilled Construction and Productivity

These questions address practical concerns Carolinas construction executives and field leaders often raise when considering multiskilled crew strategies.

How long does it take to develop a multiskilled crew on typical Carolinas construction projects?

Expect three to six months to pilot multiskilled roles on a single crew using existing workers who have adjacent experience. Fully integrating multiskilling into apprenticeship and training plans across a firm of any scale typically takes 12 to 24 months, depending on the number of trades and the complexity of your project mix.

Can multiskilled workers perform tasks that normally require a state license in North or South Carolina?

No. Multiskilled workers must not perform tasks that legally require a specific license unless they personally hold that license. Contractors should work closely with their licensing boards and safety staff to confirm which adjacent tasks are permissible. This protects both the worker and the firm.

Does multiskilling mean paying workers more, and how do contractors budget for that?

Many contractors create defined pay bands or premium rates for multiskilled workers, reflecting their broader capability. They recover these costs through higher construction productivity, fewer delays, reduced turnover, and lower re-mobilization expenses. Higher worker income also supports retention, reducing the long-term cost of recruiting and onboarding.

How does multiskilled construction affect safety metrics like recordable rates and EMR?

When implemented with proper training and supervision, multiskilling can support safety performance by reducing rushed work, trade stacking, and last-minute call-ins. ABC National’s research showed a TRIR of 0.74 for multiskilled crews, 57% below the industry benchmark. The key is to monitor safety data carefully and invest in training and equipment for every task a worker is authorized to perform.

What is the first practical step a Carolinas contractor should take after reading this briefing?

Identify one upcoming project where a small, well-defined multiskilled pilot makes sense. Choose a crew with strong field leadership, map the adjacent tasks, and set clear boundaries. Then contact ABC Carolinas to align the pilot with available apprenticeship, safety, and leadership training resources. Start with knowledge you already have, measure the results, and build from there.